TUSCALOOSA, AL-Fairly dry weather has allowed crews building a 225,000-square-foot expansion of the body shop at the Mercedes-Benz assembly plant to get about two to three weeks ahead of schedule. Approximately 35 percent of the addition’s steel framing has been installed and some 80 percent of the addition's concrete foundation is done.MORE